back to Index of Bid Openings

 

DEPARTMENT OF TRANSPORTATION

HARBORS DIVISION

 

PROJECT NO.:       H. C. 10271

 

PROJECT TITLE:       REPLACE BOLLARDS AT PIERS 19-20, HONOLULU HARBOR, OAHU

 

BID OPENING:       2:00 P.M.  SEPTEMBER 8, 2005

 

ESTIMATE:                   $75,000 – 125,000

 

 

BIDDER

BOND

BID AMOUNT

IDEAL CONSTRUCTION

BB

90,553.00

HARON ENGINEERING

BB

84,500.00

ABHE &  SVOBODA, INC.

BB

96,770.00

HAWAIIAN DREDGING CON.

BB

63,730.00

MEGA CONSTRUCTION

BB

84,350.00

WALTER ARAKAKI, GEN. CON.

BB

93,852.00

THURSTON-PACIFIC

BB

58,355.00

SEA ENGINEERING

BB

57,390.00

R. I. NAMBA CONSTRUCTION

BB

109,355.00

SITE ENGINEERING

BB

63,400.00

 

 

 

 

 

 

 

SUBS:            HONOLULU PAINTING

            VUICK ENVIRONMENTAL CONSULTANTS

           

 

 

Read by:____________________________Witnessed by:_____________________________