DEPARTMENT OF TRANSPORTATION
HARBORS DIVISION
PROJECT NO.: H. C. 70050
PROJECT TITLE: REPAIR WATERLINE AT PIER 2,
BID OPENING: 2:00 P.M. APRIL 30, 2009
ESTIMATE: $180,000
|
BIDDER |
BOND |
BID AMOUNT |
|
KOGA ENGINEERING |
BB |
$188,000.00 |
|
BCP CONSTRUCTION |
BB |
$168,762.00 |
|
MICHELLE
SAKAMOTO |
BB |
$134,700.00 |
|
SITE ENGINEERING |
BB |
$254,800.00 |
|
|
BB |
$165,458.00 |
|
EARTHWORKS |
BB |
$198,000.00 |
|
|
BB |
$254,562.00 |
|
AINA SITE |
BB |
$217,953.00 |
|
GOODFELLOW BROS. |
BB |
$210,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
SUBS: INTEGRATED CONSTRUCTION
JAS. W.
GLOVER
PAUL’S ELECTRICAL
JD PAINTING & DECORATING
SIMMONS STEEL
PURAL WATER
Read by:____________________________Witnessed
by:_____________________________